Snoeyenbos Hall Renovation

Lounge
Construction is underway for the Snoeyenbos Hall Renovation. Demolition began in early December and is being overseen by Foss Architect & Interiors. Wick Construction, Grotberg Electric, and Manny Mechanical are also on the job.

This major project consists of a complete interior remodel. The main features will include:
- 2 and 3 bedroom complexes with a private, full bathroom on each of the four floors
- updated lounge on each floor
- study room on each floor
- large, main lounge located on the first floor
- full kitchenette on the first floor
- exercise/fitness room
- air conditioning throughout the entire building

1/11/2011: The demolition stage has been completed and ahead of schedule. The next phase of construction will be to put in steel studs and sheet rock the new walls. The sprinkler system will also be added in the coming weeks and electrical work will be continuous throughout the entire project.

2/14/2011: Work continues and much progress has been made. The 4th floor electrical work is completed as well as the sheet rock. Crews are waiting for the fan coils to be installed before painting. 3rd floor has been framed and sheet rock is being put up. The electrical work is close to being completed. 2nd floor has the walls all laid out and electrical work will being in the near future. The main sewer lines have been completed on the 1st floor.

3/7/2011: Crews continue to work hard and stay ahead of schedule over in Snoeyenbos. Here is an update of the work being done at this time:
4th floor's electrical work is complete (minus the hardware) and the sheet rock is being taped. 3rd floor's electrical work is 80% complete. 2nd floor's electrical work is 80% complete 1st floor's the steel framework has been put up. Interesting fact: So far it has taken three semi-loads of sheetrock for the walls that are in place. More sheetrock will be needed to finish the walls on 2nd and 1st floor.

3/21/2011: Crews continue to work hard and stay ahead of schedule over in Snoeyenbos. Here is an update of the work being done at this time:
4th floor's sheetrock is being primed. 3rd floor's mudding and sanding of sheetrock is in progress. 2nd floor's sheetrocking in progress. 1st floor's framework is complete.
**The sewer and domestic water systems are completed
**Fan coils have arrived today and will be installed later this week.

4/21/2011: **All fan coil units have been installed.

4/25/2011: Crews continue to work hard and stay ahead of schedule over in Snoeyenbos. Here is an update of the work being done at this time:
4th floor's The lighting, cabinets and ceramic tile flooring is in the process of being installed in the suite bathrooms. 3rd floor's The 1st coat of primer has been applied and then crews can begin painting. 2nd floor's The sheetrock is completely done. 1st floor's The sheetrock will be completed early this week.
**100 tons of a/c unit will be delivered the week of May 5th.
** All mechanical work will be completed by the middle of May.

The whole project has been going smoothly and the crews will have no problem with meeting the scheduled completion date.


The projected completion date of the renovation is July 2011.
For more pictures of the Snoeyenbos Hall Renovation view the Picture Slideshow.